On Tuesday, Sept. 8, a truck with a raised bed hit the traffic signal at Glassford Hill Road and Santa Fe Loop Road. The Town of Prescott Valley reported "significant damage." Public Works crews, Prescott Valley PD and the Town's signal contractor got temporary signals running again. Two days later, southbound Glassford Hill was fully closed from 9 a.m. to 2 p.m. for repairs, with traffic detoured through Santa Fe Loop and Tuscany Way.
Seven weeks later, on Monday, Oct. 26, the Town scheduled crews to install traffic signal poles at that same intersection, with intermittent stops of up to 15 minutes. That intersection sits in the middle of the most disruptive road project in town this year: the Glassford Hill Road Widening from Long Look Drive to State Route 89A. Paving on its second phase was tentatively scheduled for this week, weather permitting. The retaining walls along the roadside take much longer to finish than the asphalt does.
Asphalt went down early in phase one, and work kept going
Phase one shows how this project actually moves. Asphalt Paving & Supply started the week of Feb. 16, 2026. Here's how the year has gone, based on the Town's notices and the weekly updates in Signals AZ:
| Date in 2026 | What happened on Glassford Hill Road |
|---|---|
| Week of Feb. 16 | Construction began, Long Look Drive to SR 89A |
| Mid-March | Excavation, drainage culverts, retaining walls and a new effluent water main between Bear Path and Ainsley Way |
| April 19 | Effluent main reported complete; first-phase new lanes being paved |
| April 29 | New traffic pattern on new lanes from just north of Long Look to just south of Spouse Drive |
| June 19 | Final paving and striping finished in phase one |
| Week of June 29 | Phase two began, Spouse Drive to the southern Granville Parkway intersection |
| Aug. 29 | Phase-one landscaping and retaining walls still underway |
| Oct. 23 | Phase two still in excavation and subgrade prep, walls, curb, gutter and sidewalk |
| Week of Nov. 2 | Phase-two paving tentatively scheduled |
In phase one, drivers were on new lanes about ten weeks after construction began. Final striping came seven weeks after that. Then, two months after striping, the August update still listed retaining walls and landscaping in that same stretch. Phase two has gone slower to its first paving date. Its crews have spent about 18 weeks on excavation, subgrade and walls between Spouse Drive and Tuscany Way, and the asphalt still hasn't gone down.
So the paving scheduled this week is a milestone. It isn't the end of work in that segment, though. If phase two follows phase one, curb, sidewalk, wall and landscaping crews will stay in the corridor after the new surface is striped.
Why a concrete wall sets the calendar
The Town's project page explains the slow part directly. Retaining and buried walls are going in where there isn't enough room for a gradual slope, so the road can widen without cutting into neighboring properties. Each wall goes through steps the project page describes, and several of them can't be rushed:
- Crews dig down to bedrock or engineered soil before setting forms.
- Ironworkers build a steel rebar cage, and drainage pipes go in at set intervals.
- Each concrete truck is tested on site for consistency, air content and temperature, and any load that fails is turned away.
- Backfill goes in small lifts, with moisture tests at each level so the road doesn't dip later.
- Rain fills open excavations and leaves soil too wet to dig or compact.
The constraint the Town spells out is curing time. In its words, concrete takes "up to 28 days to reach full design strength before heavy equipment or backfill material can press against it." A paving crew can cover a segment in a week. A wall needs about a month before anything can lean on it. On a corridor that needs walls from one end to the other, that month sets the pace.
The tan concrete going up along the road has a name. It's a colored mix called "San Diego Buff," chosen to blend with the surrounding landscape.
The finish date has already moved once
When the Town announced the project in February, it gave completion as "late-November 2026," and Signals AZ carried the same timeline. The June 19 project eNews still said late November. The current project page now says "late-December 2026, contingent on weather or other unforeseen circumstances." The Town hasn't given a reason for the change.
The bigger slip came before any digging. In July 2024, at the second and final design open house at the Prescott Valley Police Department on East Skoog Boulevard, the Town said construction was "tentatively slated to begin at the end of 2024." It actually started in mid-February 2026, about 14 months later.
The Town calls late December a target, not a fixed date. Its project page lists rain and wet soil among the conditions that can halt excavation and compaction.
What the $13.9 million buys at the curb
On Jan. 8, 2026, Public Works Director Heather Ruder sent the Town Council a staff report recommending the construction contract go to Asphalt Paving & Supply, the lowest responsive bidder, for $13,933,333.33 plus a 10% owner contingency. The report lists the full scope:
- A third northbound lane and a third southbound lane
- Curb and gutter
- Sidewalk
- Drainage improvements
- Paved shoulders
- A multi-use pathway
- Signal upgrades
- An effluent line extension
The pathway, sidewalks and shoulders matter to people who walk and bike, not only to drivers. The Town describes Glassford Hill as the main link between SR 69 and SR 89A, with "limited traffic flow and pedestrian/bicyclist accessibility" today.
The money traces back to House Bill 2234, which set aside $9.9 million from the state General Fund in fiscal 2023–24 for Glassford Hill Road improvements, on the condition that Prescott Valley show a commitment of at least $1.1 million in matching funds from non-state sources. In March 2024, with plans about 30% designed, a technical committee meeting of the regional planning group then called CYMPO, now the Yavapai Plan, recorded about $12 million available for the Long Look to SR 89A segment. The bid that came in nearly two years later was close to $2 million above that figure, before contingency.
North of Granville Parkway, no published dates
Every update since summer has focused on the Spouse Drive to Granville Parkway segment. The project's contract limits run all the way to SR 89A. For the section north of Tuscany Way and Granville Parkway, the Town says only that wall work will continue "as crews move towards SR 89A." It has posted no separate phase name or start date for that part. If you drive between Granville and 89A, the late-December target covers your stretch too, but the calendar has fewer steps posted for it.
A few rules have held the whole time and still apply:
- One lane in each direction stays open throughout construction.
- Posted work hours have been 7 a.m. to 7 p.m. on weekdays.
- Businesses, schools and residential communities stay accessible, though sidewalks may close at times.
- Short full stops happen during specific jobs like signal-pole installation, which the Town announces ahead of time.
The corridor is also busier than it was in the spring. Signals AZ reported that ALDI opened its first Prescott Valley store on Thursday, Oct. 15, at 3330 N. Glassford Hill Road, in the Kohl's shopping center between Kohl's and Walmart. Shoppers lined up for the ribbon cutting and the 9 a.m. opening.
For week-by-week changes, the project hotline is 928-582-2727. You can sign up for the weekly email updates on the project page or by writing to [email protected].
If you own a home off Glassford Hill Road, the new lanes, sidewalks and multi-use pathway will change daily life near you, and buyers will see that corridor differently in 2027 than they do now. If you'd like to know where your home's value stands while the work wraps up, Paula Stears Thomas and the PST: Premier Sales Team can give you a clear local read. Get your free home valuation.